2018 Downtown Construction Updates

November 28, 2018 - D Construction recently completed installation of the parking bays and started installing piers, planters, and structural soil. The electricians have completed installation of conduit on the 900 block of State Street. Progress since Wednesday, 11/21 has been minimal due to holiday restrictions and the storm/blizzard we experienced.

November 21, 2018 - As of Monday, 11/19, all water services have been transferred to the new watermain and the old State Street watermain has been retired. D construction has also paved the parking bay on the east side of the 800 and 900 blocks of State Street.

November 7, 2018 - D Construction has completed watermain on 9th Street. Gravity wall caps have been poured on the east side of the 900 block of State Street and pedestrian traffic has been moved in front of the buildings. Removal for the new parking bay on the east side of the 800 block of State Street has also been completed.

October 31, 2018 - D Construction started installing watermain on the south side of 9th Street, working east towards Hamilton Street. Following installation, the main will be tested and chlorinated so that the contractor can continue installation of water services.

October 24, 2018 - The contractor, D Construction, completed gravity wall and water service installation on the east side of the 900 block of State Street. Watermain installation has been completed on the east side of the 1000 block of State Street.

October 17, 2018 - D Construction has completed demolition of the existing vaulted sidewalks. Installation of gravity walls at 908, 910/912, and 916/920 State Street has been completed. Watermain was pressure-tested and chlorinated last week on the east side of the 900 block of State Street. Concrete sidewalk was poured on the west side of the 1000 block of State Street. Only one water service - which requires specialized work - remains on the block.

October 9, 2018 - The contractor, D Construction, finished up watermain work in the 10th Street intersection last week and the road has been reopened. The watermain on the 900 block of the east side of the street has been completed. Sidewalk vaults from 908 State Street to 922 State Street have been removed. D Construction has started prepping and forming for gravity walls at these locations.