- Home
- Government
- Departments
- Engineering
- Construction Projects
Construction Projects
Well 15 - Water Treatment Facility
Construction of the Well 15 - Ion Exchange Water Treatment Plant (WTP) was financed by the Drinking Water State Revolving Fund (SRF). The SRF is administered by the Illinois Environmental Protection Agency (IEPA) with federal funding from the U.S. Environmental Protection Agency (EPA). This project includes the long-term construction of a new Water Treatment Plant (WTP). Improvements made to current piping system will allow connectivity to the new water treatment plant's distribution system.
Once complete, this WTP will improve water quality for the residents and businesses in Lockport by providing higher quality water than the existing wells. SRF programs operate in each state to provide communities the resources necessary to build, Maintain, and improve the infrastructure that protects one of our most valuable resources: water.
Contractors
Design Services: Strand Associates, Inc.
Construction Services: Thieneman Construction, Inc.
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | September 2019 | Complete |
Construction | Spring 2020 | In Progress |
Latest Updates
Month | Year | Summary |
---|---|---|
August | 2021 | Continued start up activities. Substantial completion met. Punchlist work has begun. |
July | 2021 | Treatment plant start up has begun. |
May | 2021 | Crews currently evaluating start up complications. Preparations for treatment start up has begun. |
April | 2021 | Well start up operations have begun. Final punch list work in progress. |
March | 2021 | Well Pump and motor installed. Preparations have begun for testing, disinfection, and start up. |
February | 2021 | Well house construction complete. Start up and testing anticipated this month. |
November | 2020 | Underground utility work complete. Well house instrumentation work started. Parking lot paving to begin soon. |
3rd & Hamilton Water Main Replacement & Roadway Reconstruction
Utility infrastructure improvements include storm water management consisting of the installation of new inlets, manholes and storm sewer pipe, new water main and water service constructions, and related parkway restoration including sodding and temporary erosion control.
Location Details
- 3rd Street - Washington to Hamilton
- Hamilton Street - 4th Street to 2nd Street
- Hamilton Street - Franklin to Morgan
Contractors
Engineering Services: City of Lockport
Construction Services: Austin Tyler Construction
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | January 2022 | Complete |
Construction | February 2022 | In Progress |
Recent Updates
Month | Year | Summary |
---|---|---|
May | 2022 | Water Main installation complete. Storm sewer installation complete. Sidewalk and driveway installation complete. Curb and asphalt binder installation complete. Austin Tyler has begun preparation for topsoil and sod installation. |
February | 2022 | Tree removal complete. Sidewalk removal began in preparation for water main installation. Water main installation began 2-24-22. |
Kelvin Grove Rear Yard Water Main Replacement Project
Utility infrastructure improvements include storm water management consisting of the installation of new inlets, manholes and storm sewer pipe, new water main and water service constructions, and related parkway restoration including sodding and temporary erosion control.
Contractors
Engineering Services: Chamlin & Associates
Construction Services: Austin Tyler Construction
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | January 2022 | Complete |
Construction | February 2022 | In Progress |
Recent Updates
Month | Year | Summary |
---|---|---|
May | 2022 | 65 water services installed on Milne, Maple, and 7th Street. Water Main installation complete on Holly from Read to Summit. Water Main installation complete on 8th from Read to Summit. Water main installation on 8th from Summit to Adams to begin after school is on summer break. Austin Tyler has begun scheduling water service replacements on Holly and 8th. |
February | 2022 | Austin Tyler has begun reaching out to residents within project limits to set up initial water service inspections. Crews have begun replacing water services on Milne, Maple, and 7th. |
2022 Roadway Patching Project
This project includes removing and patching roadways throughout Lockport that cause repeated pot holes.
Contractors
Engineering Services: City of Lockport
Construction Services: McGill Asphalt
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | April 2022 | Complete |
Construction | May 2022 | In Progress |
Recent Updates
Month | Year | Summary |
---|---|---|
May | 2022 | City Council awarded McGill Asphalt the 2022 Roadway Patching Project on 4-20-22. Pre construction meeting scheduled for 5-5-22. |
2022 Resurfacing Project
This project includes the resurfacing of Farrell Rd from Bruce Rd to 151st Street as well as 151st Street from Farrell to Gougar. Project also includes curb removal and replacement, sidewalk installation, and storm sewer repairs.
Contractors
Engineering Services: Christopher Burke Engineering
Construction Services: PT Ferro Construction
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | March 2022 | Complete |
Construction | May 2022 | In Progress |
Recent Updates
Month | Year | Summary |
---|---|---|
May | 2022 | City Council awarded PT Ferro the 2022 Resurfacing Project on 4-6-22. Pre construction meeting scheduled for 5-4-22. |
2021 Streetscape Project
This project includes streetscape improvements to State Street from 10th to 11th and 9th Street from State to Hamilton. Improvements include sidewalk replacement, brick paver installation, planter box installation, and lighting improvements.
Contractors
Engineering Services: V3 Companies
Construction Services: Dunteman Construction
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | June 2021 | Complete |
Construction | June 2022 | In Progress |
Recent Updates
Month | Year | Summary |
---|---|---|
May | 2022 | Sidewalk removal activities to begin in mid to late June. |
WWTP Phase I Improvements
This project includes upgrading existing Division Street Waste Water Treatment Plant influent storm water processing capacity to allow for greater wet weather processing capabilities using the addition of a wet weather force main.
Contractors
Engineering Services: Baxter & Woodman
Construction Services: Williams Brothers
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | September 2021 | Complete |
Construction | June 2022 | In Progress |
Recent Updates
Month | Year | Summary |
---|---|---|
May | 2022 | Williams Brothers currently receiving materials and equipment in preparation for construction activities in Summer 2022. |
Canal Bike Path Project
This project includes the installation of an asphalt bike path from 6th street to second street along the I&M Canal.
Contractors
Engineering Services: City of Lockport
Construction Services: Schroeder Asphalt
Milestones
Phase | Start Date | Status |
---|---|---|
Pre-Construction | September 2021 | Complete |
Construction | April 2022 | In Progress |
Recent Updates
Month | Year | Summary |
---|---|---|
May | 2022 | Tree removal complete. Schroeder has begun the stone removal process in preparation for placement of asphalt. |